Ampd Energy · IEC variant · Rev 1.3, 29 April 2026
Ampd 200
A mobile battery energy storage system made by Ampd Energy, for demanding construction and industrial sites. The smaller of the two units. It is typically considered where the sustained load sits comfortably below its nominal output and space or lifting capacity is limited.
- Nominal output
- 193kW
- 214 kVA
- Nominal DC energy
- 215kWh
- Rated capacity, not usable AC energy
- Peak, up to 10 seconds
- 292kW
- Overload rating, time-limited
- Maximum charging input
- 205kW
- Unit limit, not site supply
Where it is considered
- A single tower crane or hoist with short lifting peaks
- Construction temporary power where the average load is modest but a generator has been sized for the peaks
- A limited grid connection that covers the average demand but not the peaks
- Colder sites: its listed operating range extends lower than the Ampd 400
What an assessment checks
- That sustained demand stays within nominal output, with peaks inside the overload durations
- Daily energy use against usable energy, which is confirmed in assessment
- The charging supply actually available on site
- Access and lifting for a unit of up to 5,500 kg
Suitability is a judgement about your load, supply and site. It is made in a technical assessment, not from a specification table.
Output ratings and their durations
The Ampd 200 sustains its nominal output. Above that it has two overload ratings, each limited in time. The brochure does not set out the conditions for repeated overloads, so a duty with frequent peaks is checked by an engineer.
- Nominal output193 kW / 214 kVA
- Overload, up to 60 seconds233 kW / 248 kVA
- Overload, up to 10 seconds292 kW / 297 kVA
Specifications
| Specification | Ampd 200IEC · Rev 1.3 · 29 April 2026 |
|---|---|
| Output | |
| Nominal output power | 193 kW / 214 kVA |
| Nominal output current at 380 / 400 / 415 Vac | 325 / 309 / 298 A |
| Overload output, up to 60 secondsTime-limited rating, not continuous output. | 233 kW / 248 kVA |
| Overload current, up to 60 seconds, at 380 / 400 / 415 Vac | 377 / 358 / 345 A |
| Overload output, up to 10 secondsTime-limited rating, not continuous output. | 292 kW / 297 kVA |
| Overload current, up to 10 seconds, at 380 / 400 / 415 Vac | 452 / 429 / 414 A |
| Energy storage | |
| Rated nominal DC capacityNominal DC capacity. Usable delivered AC energy is lower and is confirmed per project. | 215 kWh |
| Battery cell type | CATL lithium iron phosphate (lfp) |
| Rated battery cell lifeCell rating. The brochure states it does not equal warranted cycles. | 9,000 cycles |
| Charging input | |
| Maximum charging powerUnit limit. Actual charging depends on the supply available on site. | 205 kW |
| Maximum charging current at 380 / 400 / 415 Vac | 312 / 297 / 286 A |
| Electrical | |
| Voltage range | 380 to 415 Vac (3Ph + N + PE) |
| Frequency, as printed | 50 / 60 ± 2.5 Hz |
| Generator integration | |
| Supported configuration | Ampd 200 connected with 1 generator |
| Microgrid controller compatibility | ComAp or DeepSea |
| Recommended maximum generator capacityA recommended maximum, not a minimum or default generator size. | 350 kVA |
| Mechanical | |
| Ambient operating temperature | −30 to +55 °C (derating from 45 °C) |
| Dimensions (L × W × H) | 2.40 × 2.15 × 2.20 m |
| Maximum wet weightActual weight depends on the optional features fitted. | 5,500 kg |
| Ingress protection: batteries and HVAC | IP67 |
| Ingress protection: container enclosure | IP55 |
| Corrosion protection (standard) | C3 |
| Other | |
| Fire suppression system | Aerosol agent |
| Thermal management and coolant | Liquid cooled, ethylene glycol |
| Connectivity | Cellular 4G |
| Warranty durationDuration only. Warranty terms and any warranted throughput are confirmed in a proposal. | 5 years |
Source: Ampd 200 IEC brochure, Rev 1.3, dated 29 April 2026. Manufacturer-published figures for the IEC variant, not independently tested. Specifications can change, so the current data sheet for your territory is confirmed in a project proposal. Document 760-00013, page 2.
Optional equipment
None of the following is part of the standard specification. Each is fitted only when specified, and affects weight and applicable certifications.
| Option | As listed | Standard fit? |
|---|---|---|
| Serial charging systemRated power of the optional serial charging system. Separate from the main charging input. | 40 or 80 kW | No, optional |
| Direct DC MPPT controllerFor direct DC solar input. Applies only when the option is fitted. | 60 kW (input voltage up to 900 Vdc) | No, optional |
| Power interconnect options | Powerlock, Camlock | No, optional |
| Enhanced corrosion protectionStandard corrosion protection is C3. | C4 | No, optional |
Certifications as listed
These are the entries in the brochure, with their scope. They are listings, not certificates: the documents for a specific configuration are obtained as part of a project.
- System level
- IEC 62040-1
- Power electronics
- IEC 62477-1
- IEC 61851-1: Units equipped with serial chargers only
- IEC 61851-23: Units equipped with serial chargers only
- IEC 62109-1: Units equipped with MPPT controllers only
- EMC
- IEC 61000-6-2
- IEC 61000-6-4
- IEC 62040-2
- Battery
- IEC 62040-1
- IEC 62619
- UL 9540A (cell): Cell-level test listing. The brochure does not list UL 9540 system certification.
- Transportation
- UN 38.3 (road and sea)
Manufacturer statements
“Up to 90% reduction in carbon footprint”
Manufacturer statement, compared to generators of similar capacity. Not a forecast for a particular site.
A battery discharging on site produces no exhaust there. Overall emissions depend on how it is charged: a battery charged by a diesel generator is not zero-emission power.
Ampd 200 questions
What is the continuous output of the Ampd 200?
The Ampd 200 IEC brochure (Rev 1.3) lists a nominal output of 193 kW / 214 kVA. Its higher figures are overload ratings: 233 kW / 248 kVA for up to 60 seconds, and 292 kW / 297 kVA for up to 10 seconds. They are time-limited and are not continuous output.
How long will the Ampd 200 run?
Runtime depends on your load. The brochure lists 215 kWh of rated nominal DC capacity, which is not the same as usable AC energy delivered to your equipment. Usable energy, losses and reserve are confirmed in a project assessment.
Is the 9,000-cycle figure a warranty?
No. It is the rated life of the battery cells, where a cycle is one full charge and full discharge. The brochure states that rated cycle life does not equal warranted cycles. The listed warranty duration is 5 years; the full terms are confirmed in a proposal.
Can the Ampd 200 be used in the United States or Canada?
The published data covers the IEC variant for 380 to 415 Vac supplies. Its 50 / 60 Hz entry does not establish a North American voltage variant, and the brochure lists UL 9540A at cell level only. The applicable variant and approvals are confirmed for each North American project.
Tell us about the site for a project-specific proposal